At Workbench, work continues twenty-four hours a day, every day of the week. Everyone participates, but local quality coordinators and central quality functions play a key role. At Workbench, work continues twenty-four hours a day, every day of the week.…

IMARIKA SACCO LIMITED

Leave a comment Post in work

CLIENT:                            IMARIKA SACCO LIMITED Contract amount:                   10,060,000.00 Project start date:                  23/11/2015 Project completion date:          23/01/2016 (100% Complete)

CHINA CIVIL ENGINEERING

Leave a comment Post in work

CLIENT:             CHINA CIVIL ENGINEERING CONSTRUCTION CORPORATION LIT WORK:               CIVIL WORKS- DUMPING & BACKFILLING EXCAVATED AREAS PROJECT:         DONGO-KUNDU BYPASS MOMBASA PERIOD:             OCTOBER – DECEMBER 2015